- >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
- >Amount claimed: EUR 267.7 million
- >Amount awarded: EUR 28,080,000
- >Valuation method: income-based approach
- > Interest rate: host State's sovereign bonds (10-year)
- >Costs of arbitration: USD 1,431,480.72
- >Award legal costs: Claimants were awarded EUR 2,373,909.24 (50% of legal costs for jurisdiction and liability phase)
- >Award costs of arbitration: Costs follow the award
ARBITRAL DECISIONS
30 December 2019 Decision on Jurisdiction, Liability and Certain Issues of Quantum | 18 December 2020
|
1 December 2020 |
|