- >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
- >Amount claimed: EUR 42 million
- >Amount awarded: USD 29.3 million
- >Valuation method: income-based approach (discounted cash flow)
- > Interest rate: host State's sovereign bonds (10-year)
- >Costs of arbitration: USD 1,042,994.37
- >Award legal costs: Claimants were awarded USD 2,206,586.56 (75% of legal costs)
- >Award costs of arbitration: Respondent bears 75% of the costs
ARBITRAL DECISIONS
13 August 2019 Dissent on Liability and Quantum of Professor Philippe Sands QC | 6 September 2019 |
RECTIFICATION PROCEEDING
| 28 October 2019 - Decision on the Rectification of the Award |