- >Subject matter of the dispute: Claims arising out of the Government’s alleged failure to make a retention payment for the construction of two 254-megawatt electric power plants, and of unlawfully terminating the agreement relating to the refinery
- >BIT Invoked: Turkey-Turkmenistan BIT
- >Amount claimed: at least EUR 51,702,697.9 + USD 15,650,000
- >Amount awarded: ZERO
- >Costs of arbitration: USD 251,780.56
- >Award legal costs: Respondent was awarded USD 857,210.7 (90% of legal costs)
- >Award costs of arbitration: Costs follow the award
ARBITRAL DECISION
6 April 2020 |