Masdar Solar & Wind Cooperatief U.A. v. Spain, ICSID Case No. ARB/14/1

  • >Claimant : Masdar Solar & Wind Cooperatief U.A.
  • >Nationality : Netherlands
  • >Respondent : Spain
  • >Procedural rules applied : ICSID
  • >Chair : John Beechey
  • >Arbitrator appointed by Claimant : Gary Born
  • >Arbitrator appointed by Respondent : Brigitte Stern
  • >Invoked instruments : ECT
  • >Articles mentioned : Article 36 (7)
  • , Article 21 (7)
  • , Article 10 (1)
  • , Article 1 (2)
  • , Article 1 (3)
  • , Article 1 (6)
  • , Article 1 (10)
  • , Article 13
  • , Article 16
  • , Article 17
  • , Article 25
  • , Article 26
  • >Case status : Award rendered
  • >Year of the award or agreement : 2018
  • >Follow-on proceedings : Pending ICSID annulment proceedings
  • >Year of registration : 2014

  • >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
  • >Amount claimed: EUR 260 million
  • >Amount awarded: EUR 64.5 million
  • >Costs of arbitration: USD 1,151,994.59
  • >Award legal costs: Each party bears its legal and other expenses
  • >Award costs of arbitration: Parties share costs equally

 

ARBITRAL DECISION

16 May 2018

Arbitral Award

SUPPLEMENTARY DECISION PROCEEDINGS 

ANNULLMENT PROCEEDINGS

ENFORCEMENT PROCEEDINGS (United States)