- >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
- >Amount claimed: EUR 132.1 million
- >Amount awarded: EUR 30,875,000
- >Costs of arbitration: USD 893,685.74
- >Valuation method: income-based approach (discounted cash flow)
- >Interest rate: EURIBOR (12-month) + 1%
- >Award legal costs: Each party bears its own legal costs
- >Award costs of arbitration: Parties share costs equally
ARBITRAL DECISIONS
9 March 2020 Decision on Jurisdiction, Liability, and Directions on Quantum | 5 August 2020 |