>Subject matter of the dispute: Claims arising out of a series of measures that allegedly delayed and frustrated the claimant’s biomass power plant project, including the cancellation of a power purchase agreement with the Energy Market Operator and legislative changes that allegedly deprived the claimant of its status as an eligible power producer
>Amount claimed:EUR 71.1 million
>Amount awarded: ZERO (breach of the ECT but no damages awarded)
>Costs of arbitration: N/A
>Award legal costs: Claimant was awarded EUR 1.1 million (25% of legal costs)
>Award costs of arbitration: Costs follow the award